Tell us what you think about our site...
| Welcome to the Borough of Broxbourne | What is New | Website Map | Search | Help menu | Complaint procedure | Privacy statement | Online feedback | List Access Keys |

Demolition of buildings

Demolition of a buildingUnder Section 80 of the Building Act 1984 anyone carrying out demolition work is required to notify the Council by completing and submitting a demolition application form.

 

The Council then has six weeks to respond with appropriate notices and consultation under Sections 81 and 82 of the Act. Further details can be found on the reverse of the application form. There is no charge for this process.

 

Notification of a demolition is not required where:

  • the building is less than 1750 cubic feet, measured externally (approximately 50 cubic metres).
  • the demolition is of an internal part of any occupied building, which is intended to remain occupied.
  • the building is a greenhouse, conservatory, shed or prefabricated garage, even if the building forms part of a larger building.
  • certain agricultural building, unless it is near or touching another building that is not an agricultural building.
  • a demolition order under the Housing Act 1985 has been served.